How long does a Single Construction Permit permit take in Saddle Ridge, Calgary?
Median days · Applied → Issued
25 days
Sample: 174 permits, last 24 months
Median days · Issued → Completed
167 days
From permit issuance to completion
City-wide median
18 days
Saddle Ridge is 7 days slower
Recent examples in Saddle Ridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14104 | New | Prominent Homes | 2026-07-27 | 2026-09-10 | 45 | $401K |
| BP2026-06439 | New | Yuvraj Homes | 2026-04-21 | 2026-08-25 | 126 | $520K |
| BP2026-13526 | New | Prominent Homes | 2026-07-20 | 2026-08-13 | 24 | $401K |
| BP2026-13006 | New | Akash Homes | 2026-07-13 | 2026-08-09 | 27 | $346K |
| BP2026-11640 | New | Akash Homes | 2026-06-24 | 2026-08-08 | 45 | $346K |