How long does a Single Construction Permit permit take in Saddle Ridge, Calgary?

Rolling 24 months · Sample: 174
Median days · Applied → Issued
25 days
Sample: 174 permits, last 24 months
Median days · Issued → Completed
167 days
From permit issuance to completion
City-wide median
18 days
Saddle Ridge is 7 days slower

Recent examples in Saddle Ridge

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14104NewProminent Homes2026-07-272026-09-1045$401K
BP2026-06439NewYuvraj Homes2026-04-212026-08-25126$520K
BP2026-13526NewProminent Homes2026-07-202026-08-1324$401K
BP2026-13006NewAkash Homes2026-07-132026-08-0927$346K
BP2026-11640NewAkash Homes2026-06-242026-08-0845$346K