How long does a Commercial / Multi Family Project permit take in Saddle Ridge, Calgary?

Rolling 24 months · Sample: 88
Median days · Applied → Issued
54 days
Sample: 88 permits, last 24 months
Median days · Issued → Completed
195 days
From permit issuance to completion
City-wide median
42 days
Saddle Ridge is 12 days slower

Recent examples in Saddle Ridge

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2025-17765New2025-09-112026-09-03357$18.1M
BP2025-17654New2025-09-102026-09-03358$9.3M
BP2026-16249ImprovementLandform2026-08-262026-09-016$2K
BP2025-11967NewKlair Homes2025-06-202026-08-27433$995K
BP2025-00669New2025-01-142026-08-12575$29.3M