How long does a Commercial / Multi Family Project permit take in Saddle Ridge, Calgary?

Rolling 24 months · Sample: 85
Median days · Applied → Issued
56 days
Sample: 85 permits, last 24 months
Median days · Issued → Completed
206 days
From permit issuance to completion
City-wide median
42 days
Saddle Ridge is 14 days slower

Recent examples in Saddle Ridge

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-20516Improvement—2026-10-262026-11-1318$10K
BP2025-16218NewChandan Homes2025-08-202026-11-09446$2.5M
BP2025-16214NewChandan Homes2025-08-202026-11-09446$2.9M
BP2025-16204NewChandan Homes2025-08-202026-11-07444$2.2M
BP2025-16203NewChandan Homes2025-08-202026-11-07444$2.5M