How long does a Commercial / Multi Family Project permit take in Saddle Ridge, Calgary?
Median days · Applied → Issued
56 days
Sample: 85 permits, last 24 months
Median days · Issued → Completed
206 days
From permit issuance to completion
City-wide median
42 days
Saddle Ridge is 14 days slower
Recent examples in Saddle Ridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-20516 | Improvement | — | 2026-10-26 | 2026-11-13 | 18 | $10K |
| BP2025-16218 | New | Chandan Homes | 2025-08-20 | 2026-11-09 | 446 | $2.5M |
| BP2025-16214 | New | Chandan Homes | 2025-08-20 | 2026-11-09 | 446 | $2.9M |
| BP2025-16204 | New | Chandan Homes | 2025-08-20 | 2026-11-07 | 444 | $2.2M |
| BP2025-16203 | New | Chandan Homes | 2025-08-20 | 2026-11-07 | 444 | $2.5M |