How long does a Residential Improvement Project permit take in Saddle Ridge, Calgary?

Rolling 24 months · Sample: 566
Median days · Applied → Issued
19 days
Sample: 566 permits, last 24 months
Median days · Issued → Completed
88 days
From permit issuance to completion
City-wide median
17 days
Saddle Ridge is 2 days slower

Recent examples in Saddle Ridge

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16074Improvement—2026-08-242026-11-1381$22K
BP2026-20422NewSolai Contracting2026-10-232026-11-1220$45K
BP2026-18018New—2026-09-202026-11-1253$51K
BP2026-19956New—2026-10-182026-11-1124$42K
BP2026-20256New—2026-10-212026-11-1020$47K