How long does a Single Construction Permit permit take in Pine Creek, Calgary?

Rolling 24 months · Sample: 655
Median days · Applied → Issued
16 days
Sample: 655 permits, last 24 months
Median days · Issued → Completed
202 days
From permit issuance to completion
City-wide median
18 days
Pine Creek is 2 days faster

Recent examples in Pine Creek

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15391NewMorrison Homes2026-08-132026-09-1129$237K
BP2026-15382NewAnthem Pine Creek Homes2026-08-132026-09-1028$369K
BP2026-15834NewShane Homes2026-08-202026-09-0920$193K
BP2026-15833NewShane Homes2026-08-202026-09-0920$185K
BP2026-15070NewSterling Homes2026-08-102026-09-0930$410K