How long does a Residential Improvement Project permit take in Pine Creek, Calgary?
Median days · Applied → Issued
14 days
Sample: 471 permits, last 24 months
Median days · Issued → Completed
85 days
From permit issuance to completion
City-wide median
17 days
Pine Creek is 3 days faster
Recent examples in Pine Creek
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16236 | Improvement | Durable Decks | 2026-08-26 | 2026-09-08 | 13 | $6K |
| BP2026-15512 | Improvement | — | 2026-08-14 | 2026-09-08 | 25 | $117 |
| BP2026-16028 | New | Symbiotic Services | 2026-08-24 | 2026-09-03 | 10 | $46K |
| BP2026-15915 | Improvement | — | 2026-08-21 | 2026-09-02 | 12 | $73K |
| BP2026-13652 | Improvement | — | 2026-07-21 | 2026-09-02 | 43 | $61K |