How long does a Residential Improvement Project permit take in Pine Creek, Calgary?

Rolling 24 months · Sample: 471
Median days · Applied → Issued
14 days
Sample: 471 permits, last 24 months
Median days · Issued → Completed
85 days
From permit issuance to completion
City-wide median
17 days
Pine Creek is 3 days faster

Recent examples in Pine Creek

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16236ImprovementDurable Decks2026-08-262026-09-0813$6K
BP2026-15512Improvement2026-08-142026-09-0825$117
BP2026-16028NewSymbiotic Services2026-08-242026-09-0310$46K
BP2026-15915Improvement2026-08-212026-09-0212$73K
BP2026-13652Improvement2026-07-212026-09-0243$61K