How long does a Commercial / Multi Family Project permit take in Pine Creek, Calgary?
Median days · Applied → Issued
51 days
Sample: 26 permits, last 24 months
Median days · Issued → Completed
158 days
From permit issuance to completion
City-wide median
42 days
Pine Creek is 9 days slower
Recent examples in Pine Creek
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10789 | New | Streetside Development | 2026-06-12 | 2026-08-25 | 74 | $1.7M |
| BP2026-12258 | New | Partners Development Group Residential | 2026-07-02 | 2026-07-22 | 20 | $732K |
| BP2026-11005 | New | Streetside Development | 2026-06-16 | 2026-07-07 | 21 | $1.6M |
| BP2026-08762 | New | Morrison Homes Calgary Multi | 2026-05-19 | 2026-06-23 | 35 | $1.9M |
| BP2026-05974 | New | Partners Development Group Residential | 2026-04-15 | 2026-04-28 | 13 | $605K |