How long does a Commercial / Multi Family Project permit take in Pine Creek, Calgary?

Rolling 24 months · Sample: 21
Median days · Applied → Issued
35 days
Sample: 21 permits, last 24 months
Median days · Issued → Completed
153 days
From permit issuance to completion
City-wide median
42 days
Pine Creek is 7 days faster

Recent examples in Pine Creek

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-18655NewStreetside Development2026-09-292026-10-1920$1.6M
BP2026-10789NewStreetside Development2026-06-122026-08-2574$1.7M
BP2026-12258NewPartners Development Group Residential2026-07-022026-07-2220$732K
BP2026-11005NewStreetside Development2026-06-162026-07-0721$1.6M
BP2026-08762NewMorrison Homes Calgary Multi2026-05-192026-06-2335$1.9M