How long does a Commercial / Multi Family Project permit take in Pine Creek, Calgary?

Rolling 24 months · Sample: 26
Median days · Applied → Issued
51 days
Sample: 26 permits, last 24 months
Median days · Issued → Completed
158 days
From permit issuance to completion
City-wide median
42 days
Pine Creek is 9 days slower

Recent examples in Pine Creek

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10789NewStreetside Development2026-06-122026-08-2574$1.7M
BP2026-12258NewPartners Development Group Residential2026-07-022026-07-2220$732K
BP2026-11005NewStreetside Development2026-06-162026-07-0721$1.6M
BP2026-08762NewMorrison Homes Calgary Multi2026-05-192026-06-2335$1.9M
BP2026-05974NewPartners Development Group Residential2026-04-152026-04-2813$605K