How long does a Residential Improvement Project permit take in Glacier Ridge, Calgary?
Median days · Applied → Issued
12 days
Sample: 543 permits, last 24 months
Median days · Issued → Completed
78 days
From permit issuance to completion
City-wide median
17 days
Glacier Ridge is 5 days faster
Recent examples in Glacier Ridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-20468 | Improvement | Pro Design Constuction | 2026-10-25 | 2026-11-13 | 19 | $29K |
| BP2026-17581 | New | Harv Homes | 2026-09-15 | 2026-11-12 | 58 | $62K |
| BP2026-20484 | Improvement | Royal Canadian Renovation | 2026-10-26 | 2026-11-10 | 15 | $57K |
| BP2026-20473 | New | Deep Gill Construction | 2026-10-25 | 2026-11-10 | 16 | $47K |
| BP2026-20472 | New | Deep Gill Construction | 2026-10-25 | 2026-11-10 | 16 | $47K |