How long does a Residential Improvement Project permit take in Glacier Ridge, Calgary?
Median days · Applied → Issued
12 days
Sample: 556 permits, last 24 months
Median days · Issued → Completed
80 days
From permit issuance to completion
City-wide median
17 days
Glacier Ridge is 5 days faster
Recent examples in Glacier Ridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15628 | New | — | 2026-08-17 | 2026-09-11 | 25 | $42K |
| BP2026-16000 | Improvement | — | 2026-08-22 | 2026-09-09 | 18 | $77K |
| BP2026-16270 | Improvement | — | 2026-08-26 | 2026-09-08 | 13 | $72K |
| BP2026-16269 | New | — | 2026-08-26 | 2026-09-08 | 13 | $47K |
| BP2026-16333 | New | Pama Homes | 2026-08-26 | 2026-09-07 | 12 | $42K |