Highlighted
How long does a Commercial / Multi Family Project permit take in Glacier Ridge, Calgary?
Median days · Applied → Issued
69 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
322 days
From permit issuance to completion
City-wide median
42 days
Glacier Ridge is 27 days slower
Recent examples in Glacier Ridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10998 | New | — | 2026-06-16 | 2026-11-02 | 139 | $961K |
| BP2026-10012 | Unspecified | — | 2026-06-03 | 2026-07-15 | 42 | $0 |
| BP2025-17372 | New | — | 2025-09-05 | 2025-12-09 | 95 | $964K |
| BP2024-26393 | Unspecified | — | 2024-12-24 | 2025-01-31 | 38 | $180K |