How long does a Single Construction Permit permit take in Rangeview, Calgary?
Median days · Applied → Issued
21 days
Sample: 717 permits, last 24 months
Median days · Issued → Completed
175 days
From permit issuance to completion
City-wide median
18 days
Rangeview is 3 days slower
Recent examples in Rangeview
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14656 | New | Stealth Homes | 2026-08-04 | 2026-09-10 | 37 | $167K |
| BP2026-14655 | New | Stealth Homes | 2026-08-04 | 2026-09-10 | 37 | $162K |
| BP2026-15212 | New | Jayman Built | 2026-08-11 | 2026-09-09 | 29 | $264K |
| BP2026-14736 | New | Rohit Communities | 2026-08-05 | 2026-09-09 | 35 | $221K |
| BP2026-14916 | New | Rohit Communities | 2026-08-07 | 2026-09-08 | 32 | $221K |