How long does a Commercial / Multi Family Project permit take in Rangeview, Calgary?
Median days · Applied → Issued
49 days
Sample: 86 permits, last 24 months
Median days · Issued → Completed
203 days
From permit issuance to completion
City-wide median
42 days
Rangeview is 7 days slower
Recent examples in Rangeview
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13804 | New | Bedrock Homes | 2026-07-23 | 2026-08-28 | 36 | $1.5M |
| BP2025-16845 | New | Avi Construction and Management | 2025-08-28 | 2026-07-17 | 323 | $1.2M |
| BP2026-02697 | New | Avi Construction and Management | 2026-02-23 | 2026-07-16 | 143 | $1.6M |
| BP2026-02694 | New | Avi Construction and Management | 2026-02-23 | 2026-07-16 | 143 | $1.9M |
| BP2025-16842 | New | Avi Construction and Management | 2025-08-28 | 2026-07-16 | 322 | $1.2M |