How long does a Commercial / Multi Family Project permit take in Rangeview, Calgary?

Rolling 24 months · Sample: 87
Median days · Applied → Issued
51 days
Sample: 87 permits, last 24 months
Median days · Issued → Completed
205 days
From permit issuance to completion
City-wide median
42 days
Rangeview is 9 days slower

Recent examples in Rangeview

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13870NewDeveraux Developments2026-07-232026-11-05105$14.3M
BP2026-13093NewHighstreet Ventures2026-07-142026-10-29107$11M
BP2026-12838New—2026-07-102026-10-20102$11M
BP2026-16288NewBedrock Homes2026-08-262026-10-1752$1.5M
BP2026-10094NewHighstreet Ventures2026-06-042026-10-08126$12.7M