How long does a Commercial / Multi Family Project permit take in Rangeview, Calgary?

Rolling 24 months · Sample: 86
Median days · Applied → Issued
49 days
Sample: 86 permits, last 24 months
Median days · Issued → Completed
203 days
From permit issuance to completion
City-wide median
42 days
Rangeview is 7 days slower

Recent examples in Rangeview

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13804NewBedrock Homes2026-07-232026-08-2836$1.5M
BP2025-16845NewAvi Construction and Management2025-08-282026-07-17323$1.2M
BP2026-02697NewAvi Construction and Management2026-02-232026-07-16143$1.6M
BP2026-02694NewAvi Construction and Management2026-02-232026-07-16143$1.9M
BP2025-16842NewAvi Construction and Management2025-08-282026-07-16322$1.2M