How long does a Single Construction Permit permit take in Mahogany, Calgary?

Rolling 24 months · Sample: 480
Median days · Applied → Issued
14 days
Sample: 480 permits, last 24 months
Median days · Issued → Completed
182 days
From permit issuance to completion
City-wide median
19 days
Mahogany is 5 days faster

Recent examples in Mahogany

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-20249NewExcel Homes2026-10-212026-11-1323$357K
BP2026-18749NewJayman Built2026-09-302026-11-1142$418K
BP2026-19975NewHopewell Residential2026-10-192026-11-1022$375K
BP2026-19915NewHopewell Residential2026-10-162026-11-1025$450K
BP2026-18347NewBaywest Homes2026-09-242026-11-1047$687K