How long does a Single Construction Permit permit take in Mahogany, Calgary?
Median days · Applied → Issued
15 days
Sample: 518 permits, last 24 months
Median days · Issued → Completed
189 days
From permit issuance to completion
City-wide median
18 days
Mahogany is 3 days faster
Recent examples in Mahogany
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15460 | New | Hopewell Residential | 2026-08-14 | 2026-08-31 | 17 | $188K |
| BP2026-15459 | New | Hopewell Residential | 2026-08-14 | 2026-08-31 | 17 | $188K |
| BP2026-14216 | New | Jayman Built | 2026-07-28 | 2026-08-27 | 30 | $323K |
| BP2026-15377 | New | Hopewell Residential | 2026-08-13 | 2026-08-26 | 13 | $192K |
| BP2026-15376 | New | Hopewell Residential | 2026-08-13 | 2026-08-26 | 13 | $192K |