How long does a Demolition permit take in Mahogany, Calgary?

Rolling 24 months · Sample: 5
Median days · Applied → Issued
12 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
62 days
From permit issuance to completion
City-wide median
4 days
Mahogany is 8 days slower

Recent examples in Mahogany

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2024-25359DemolitionRocky Cross Construction North2024-12-062024-12-137$0
BP2024-24926DemolitionRocky Cross Construction North2024-11-282024-12-1012$0
BP2024-24925DemolitionRocky Cross Construction North2024-11-282024-12-1012$0
BP2024-24909DemolitionRocky Cross Construction North2024-11-282024-12-1012$0
BP2024-24900DemolitionRocky Cross Construction North2024-11-282024-12-1012$0