How long does a Demolition permit take in Mahogany, Calgary?
Median days · Applied → Issued
12 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
62 days
From permit issuance to completion
City-wide median
4 days
Mahogany is 8 days slower
Recent examples in Mahogany
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2024-25359 | Demolition | Rocky Cross Construction North | 2024-12-06 | 2024-12-13 | 7 | $0 |
| BP2024-24926 | Demolition | Rocky Cross Construction North | 2024-11-28 | 2024-12-10 | 12 | $0 |
| BP2024-24925 | Demolition | Rocky Cross Construction North | 2024-11-28 | 2024-12-10 | 12 | $0 |
| BP2024-24909 | Demolition | Rocky Cross Construction North | 2024-11-28 | 2024-12-10 | 12 | $0 |
| BP2024-24900 | Demolition | Rocky Cross Construction North | 2024-11-28 | 2024-12-10 | 12 | $0 |