How long does a Commercial / Multi Family Project permit take in Mahogany, Calgary?

Rolling 24 months · Sample: 61
Median days · Applied → Issued
42 days
Sample: 61 permits, last 24 months
Median days · Issued → Completed
240 days
From permit issuance to completion
City-wide median
42 days
Same as Mahogany

Recent examples in Mahogany

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-17977New—2026-09-182026-10-1426$2.5M
BP2026-16860ImprovementJoshua General Contracting2026-09-032026-10-1340$17K
BP2026-13523NewAvalon Master Builder Avalon Industries2026-07-202026-08-1425$1.4M
BP2026-13095Improvement—2026-07-142026-08-0623$185K
BP2026-12804NewExcel Mahogany Townhomes2026-07-092026-07-2819$1.5M