How long does a Commercial / Multi Family Project permit take in Mahogany, Calgary?
Median days · Applied → Issued
48 days
Sample: 65 permits, last 24 months
Median days · Issued → Completed
255 days
From permit issuance to completion
City-wide median
42 days
Mahogany is 6 days slower
Recent examples in Mahogany
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13523 | New | Avalon Master Builder Avalon Industries | 2026-07-20 | 2026-08-14 | 25 | $1.4M |
| BP2026-13095 | Improvement | — | 2026-07-14 | 2026-08-06 | 23 | $185K |
| BP2026-12804 | New | Excel Mahogany Townhomes | 2026-07-09 | 2026-07-28 | 19 | $1.5M |
| BP2026-08694 | New | Avalon Master Builder Avalon Industries | 2026-05-19 | 2026-07-09 | 51 | $1.4M |
| BP2026-08461 | New | Excel Mahogany Townhomes | 2026-05-14 | 2026-06-26 | 43 | $1.5M |