How long does a Single Construction Permit permit take in Livingston, Calgary?
Median days · Applied → Issued
16 days
Sample: 617 permits, last 24 months
Median days · Issued → Completed
200 days
From permit issuance to completion
City-wide median
18 days
Livingston is 2 days faster
Recent examples in Livingston
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15242 | New | Morrison Homes | 2026-08-12 | 2026-09-09 | 28 | $302K |
| BP2026-13051 | New | Cedarglen Group | 2026-07-13 | 2026-08-25 | 43 | $261K |
| BP2026-13537 | New | Excel Homes | 2026-07-20 | 2026-08-24 | 35 | $284K |
| BP2026-11490 | New | Cedarglen Group | 2026-06-22 | 2026-08-24 | 63 | $277K |
| BP2026-14195 | New | Brookfield Residential | 2026-07-28 | 2026-08-20 | 23 | $299K |