How long does a Residential Improvement Project permit take in Livingston, Calgary?

Rolling 24 months · Sample: 694
Median days · Applied → Issued
14 days
Sample: 694 permits, last 24 months
Median days · Issued → Completed
90 days
From permit issuance to completion
City-wide median
17 days
Livingston is 3 days faster

Recent examples in Livingston

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-20078ImprovementSuncoast Enclosures2026-10-192026-11-1325$30K
BP2026-19873NewAmar Homes2026-10-162026-11-1025$55K
BP2026-21202Improvement—2026-11-052026-11-094$28K
BP2026-20073NewJas Garage Builders2026-10-192026-11-0214$42K
BP2026-18504NewCalgaryprofix Home Improvement Services2026-09-282026-10-2931$42K