How long does a Commercial / Multi Family Project permit take in Livingston, Calgary?

Rolling 24 months · Sample: 51
Median days · Applied → Issued
60 days
Sample: 51 permits, last 24 months
Median days · Issued → Completed
289 days
From permit issuance to completion
City-wide median
42 days
Livingston is 18 days slower

Recent examples in Livingston

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-09161NewDaytona Homes2026-05-252026-11-13172$998K
BP2026-17412Improvement—2026-09-112026-11-1060$250K
BP2026-13968ImprovementGrand Scale Construction2026-07-242026-10-3098$30K
BP2026-15686Improvement—2026-08-182026-10-1457$70K
BP2025-23910NewDaytona Homes2025-12-182026-09-18274$998K