How long does a Commercial / Multi Family Project permit take in Livingston, Calgary?

Rolling 24 months · Sample: 47
Median days · Applied → Issued
60 days
Sample: 47 permits, last 24 months
Median days · Issued → Completed
317 days
From permit issuance to completion
City-wide median
42 days
Livingston is 18 days slower

Recent examples in Livingston

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15275NewBrookfield Residential2026-08-122026-08-2816$875K
BP2026-11225Improvement2026-06-182026-08-2568$200K
BP2026-09992Improvement2026-06-032026-08-1876$1.3M
BP2026-02531New2026-02-192026-06-26127$2.2M
BP2026-09287NewBrookfield Residential2026-05-272026-06-1923$855K