How long does a Commercial / Multi Family Project permit take in Livingston, Calgary?
Median days · Applied → Issued
60 days
Sample: 51 permits, last 24 months
Median days · Issued → Completed
289 days
From permit issuance to completion
City-wide median
42 days
Livingston is 18 days slower
Recent examples in Livingston
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-09161 | New | Daytona Homes | 2026-05-25 | 2026-11-13 | 172 | $998K |
| BP2026-17412 | Improvement | — | 2026-09-11 | 2026-11-10 | 60 | $250K |
| BP2026-13968 | Improvement | Grand Scale Construction | 2026-07-24 | 2026-10-30 | 98 | $30K |
| BP2026-15686 | Improvement | — | 2026-08-18 | 2026-10-14 | 57 | $70K |
| BP2025-23910 | New | Daytona Homes | 2025-12-18 | 2026-09-18 | 274 | $998K |