How long does a Single Construction Permit permit take in Winston Heights/Mountview, Calgary?

Rolling 24 months · Sample: 35
Median days · Applied → Issued
35 days
Sample: 35 permits, last 24 months
Median days · Issued → Completed
318 days
From permit issuance to completion
City-wide median
18 days
Winston Heights/Mountview is 17 days slower

Recent examples in Winston Heights/Mountview

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15670NewCanbrook Homes2026-08-182026-09-0922$0
BP2026-15673NewCanbrook Homes2026-08-182026-09-0922$0
BP2026-10448NewSilver Key Homes2026-06-092026-07-2748$269K
BP2026-10450NewSilver Key Homes2026-06-092026-07-2748$269K
BP2026-06848NewMst Construction2026-04-272026-07-0367$490K