How long does a Single Construction Permit permit take in Winston Heights/Mountview, Calgary?
Median days · Applied → Issued
35 days
Sample: 35 permits, last 24 months
Median days · Issued → Completed
318 days
From permit issuance to completion
City-wide median
18 days
Winston Heights/Mountview is 17 days slower
Recent examples in Winston Heights/Mountview
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15670 | New | Canbrook Homes | 2026-08-18 | 2026-09-09 | 22 | $0 |
| BP2026-15673 | New | Canbrook Homes | 2026-08-18 | 2026-09-09 | 22 | $0 |
| BP2026-10448 | New | Silver Key Homes | 2026-06-09 | 2026-07-27 | 48 | $269K |
| BP2026-10450 | New | Silver Key Homes | 2026-06-09 | 2026-07-27 | 48 | $269K |
| BP2026-06848 | New | Mst Construction | 2026-04-27 | 2026-07-03 | 67 | $490K |