How long does a Residential Improvement Project permit take in Winston Heights/Mountview, Calgary?

Rolling 24 months · Sample: 74
Median days · Applied → Issued
25 days
Sample: 74 permits, last 24 months
Median days · Issued → Completed
204 days
From permit issuance to completion
City-wide median
17 days
Winston Heights/Mountview is 8 days slower

Recent examples in Winston Heights/Mountview

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10456ImprovementLige Constructions2026-06-092026-08-1769$60K
BP2026-10457ImprovementLige Constructions2026-06-092026-08-1769$60K
BP2026-13670Improvement2026-07-212026-08-1727$60K
BP2026-10449NewSilver Key Homes2026-06-092026-07-2748$40K
BP2026-10451NewSilver Key Homes2026-06-092026-07-2748$40K