How long does a Commercial / Multi Family Project permit take in Winston Heights/Mountview, Calgary?

Rolling 24 months · Sample: 38
Median days · Applied → Issued
111 days
Sample: 38 permits, last 24 months
Median days · Issued → Completed
382 days
From permit issuance to completion
City-wide median
42 days
Winston Heights/Mountview is 69 days slower

Recent examples in Winston Heights/Mountview

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-08678Improvement2026-05-192026-08-2598$250K
BP2026-05710NewWinter Green Homes2026-04-102026-08-19131$1.1M
BP2026-06104New2026-04-162026-08-19125$1.1M
BP2026-06094New2026-04-162026-07-25100$1.1M
BP2026-06095New2026-04-162026-07-25100$664K