How long does a Commercial / Multi Family Project permit take in Winston Heights/Mountview, Calgary?
Median days · Applied → Issued
111 days
Sample: 38 permits, last 24 months
Median days · Issued → Completed
382 days
From permit issuance to completion
City-wide median
42 days
Winston Heights/Mountview is 69 days slower
Recent examples in Winston Heights/Mountview
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08678 | Improvement | — | 2026-05-19 | 2026-08-25 | 98 | $250K |
| BP2026-05710 | New | Winter Green Homes | 2026-04-10 | 2026-08-19 | 131 | $1.1M |
| BP2026-06104 | New | — | 2026-04-16 | 2026-08-19 | 125 | $1.1M |
| BP2026-06094 | New | — | 2026-04-16 | 2026-07-25 | 100 | $1.1M |
| BP2026-06095 | New | — | 2026-04-16 | 2026-07-25 | 100 | $664K |