How long does a Demolition permit take in Winston Heights/Mountview, Calgary?

Rolling 24 months · Sample: 35
Median days · Applied → Issued
3 days
Sample: 35 permits, last 24 months
Median days · Issued → Completed
34 days
From permit issuance to completion
City-wide median
4 days
Winston Heights/Mountview is 1 days faster

Recent examples in Winston Heights/Mountview

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16781DemolitionWestern One Excavation2026-09-022026-09-042$0
BP2026-14841DemolitionGreenshield Construction2026-08-062026-08-1913$0
BP2026-15188DemolitionWestern One Excavation2026-08-112026-08-121$0
BP2026-10230DemolitionTroy Demolition2026-06-052026-08-0460$0
BP2026-12914DemolitionKingsway Builders2026-07-102026-07-133$0