How long does a Single Construction Permit permit take in Upper Mount Royal, Calgary?

Rolling 24 months · Sample: 15
Median days · Applied → Issued
67 days
Sample: 15 permits, last 24 months
Median days · Issued → Completed
445 days
From permit issuance to completion
City-wide median
18 days
Upper Mount Royal is 49 days slower

Recent examples in Upper Mount Royal

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10059NewWilliam Blake Homes2026-06-032026-07-2754$825K
BP2026-01405NewWillow and Stone Custom Homes2026-01-302026-03-3160$1.3M
BP2025-22232New2025-11-182026-01-2265$0
BP2025-19903NewMaillot Homes2025-10-092025-12-1567$762K
BP2025-17726NewMaillot Homes2025-09-102025-11-0758$284K