How long does a Demolition permit take in Upper Mount Royal, Calgary?
Median days · Applied → Issued
4 days
Sample: 14 permits, last 24 months
Median days · Issued → Completed
47 days
From permit issuance to completion
City-wide median
4 days
Same as Upper Mount Royal
Recent examples in Upper Mount Royal
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13332 | Demolition | Creative Solutions Contracting Services | 2026-07-16 | 2026-07-17 | 1 | $0 |
| BP2026-12522 | Demolition | Creative Solutions Contracting Services | 2026-07-06 | 2026-07-09 | 3 | $0 |
| BP2026-09703 | Demolition | Creative Solutions Contracting Services | 2026-05-31 | 2026-06-02 | 2 | $0 |
| BP2026-05472 | Demolition | Dynamic Dirt Works | 2026-04-08 | 2026-04-14 | 6 | $0 |
| BP2026-03356 | Demolition | Garrett Contracting | 2026-03-05 | 2026-03-06 | 1 | $0 |