How long does a Residential Improvement Project permit take in Upper Mount Royal, Calgary?
Median days · Applied → Issued
28 days
Sample: 46 permits, last 24 months
Median days · Issued → Completed
181 days
From permit issuance to completion
City-wide median
17 days
Upper Mount Royal is 11 days slower
Recent examples in Upper Mount Royal
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11763 | Improvement | — | 2026-06-25 | 2026-08-28 | 64 | $201K |
| BP2026-14550 | Improvement | Koski Pools | 2026-08-03 | 2026-08-27 | 24 | $30K |
| BP2026-14683 | Improvement | Deck King | 2026-08-04 | 2026-08-20 | 16 | $2K |
| BP2026-13479 | Improvement | Makena Homes | 2026-07-20 | 2026-08-17 | 28 | $10K |
| BP2026-11808 | Improvement | Park Landscaping | 2026-06-25 | 2026-07-14 | 19 | $50K |