How long does a Commercial / Multi Family Project permit take in Upper Mount Royal, Calgary?
Median days · Applied → Issued
50 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
175 days
From permit issuance to completion
City-wide median
42 days
Upper Mount Royal is 8 days slower
Recent examples in Upper Mount Royal
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-04816 | New | — | 2026-03-27 | 2026-06-30 | 95 | $1M |
| BP2026-05238 | Improvement | — | 2026-04-04 | 2026-04-16 | 12 | $10K |
| BP2024-23258 | Improvement | — | 2024-11-01 | 2024-11-04 | 3 | $30K |
| BP2024-15910 | Improvement | Nascent Builders | 2024-08-01 | 2024-10-28 | 88 | $275K |