How long does a Commercial / Multi Family Project permit take in Upper Mount Royal, Calgary?

Rolling 24 months · Sample: 4
Median days · Applied → Issued
50 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
175 days
From permit issuance to completion
City-wide median
42 days
Upper Mount Royal is 8 days slower

Recent examples in Upper Mount Royal

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-04816New2026-03-272026-06-3095$1M
BP2026-05238Improvement2026-04-042026-04-1612$10K
BP2024-23258Improvement2024-11-012024-11-043$30K
BP2024-15910ImprovementNascent Builders2024-08-012024-10-2888$275K