How long does a Single Construction Permit permit take in Rutland Park, Calgary?

Rolling 24 months · Sample: 4
Median days · Applied → Issued
52 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
302 days
From permit issuance to completion
City-wide median
18 days
Rutland Park is 34 days slower

Recent examples in Rutland Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-09645NewSamdisha Homes2026-05-292026-06-1618$385K
BP2025-17450NewAlberta Renaissance Homes2025-09-072025-10-2750$416K
BP2025-06458NewCalista Homes2025-04-112025-06-0454$551K
BP2024-20863NewDream Ridge Homes2024-10-012025-01-23114$488K