How long does a Single Construction Permit permit take in Rutland Park, Calgary?
Median days · Applied → Issued
52 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
302 days
From permit issuance to completion
City-wide median
18 days
Rutland Park is 34 days slower
Recent examples in Rutland Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-09645 | New | Samdisha Homes | 2026-05-29 | 2026-06-16 | 18 | $385K |
| BP2025-17450 | New | Alberta Renaissance Homes | 2025-09-07 | 2025-10-27 | 50 | $416K |
| BP2025-06458 | New | Calista Homes | 2025-04-11 | 2025-06-04 | 54 | $551K |
| BP2024-20863 | New | Dream Ridge Homes | 2024-10-01 | 2025-01-23 | 114 | $488K |