How long does a Demolition permit take in Rutland Park, Calgary?

Rolling 24 months · Sample: 6
Median days · Applied → Issued
4 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
107 days
From permit issuance to completion
City-wide median
4 days
Same as Rutland Park

Recent examples in Rutland Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-05652DemolitionWestern One Excavation2026-04-102026-04-155$0
BP2026-03798DemolitionShamrock Earthworks2026-03-122026-03-186$0
BP2025-23530DemolitionBlue Ridge Excavating2025-12-102025-12-122$0
BP2025-11461DemolitionWestern One Excavation2025-06-152025-06-183$0
BP2025-01422DemolitionAndco Excavating2025-01-272025-01-292$0