How long does a Residential Improvement Project permit take in Rutland Park, Calgary?
Median days · Applied → Issued
20 days
Sample: 19 permits, last 24 months
Median days · Issued → Completed
122 days
From permit issuance to completion
City-wide median
17 days
Rutland Park is 3 days slower
Recent examples in Rutland Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11705 | Improvement | — | 2026-06-25 | 2026-08-27 | 63 | $48K |
| BP2026-11312 | New | — | 2026-06-19 | 2026-07-07 | 18 | $5K |
| BP2026-09646 | New | Samdisha Homes | 2026-05-29 | 2026-06-16 | 18 | $61K |
| BP2026-08711 | New | Alberta Renaissance Homes | 2026-05-19 | 2026-06-08 | 20 | $70K |
| BP2026-06316 | Improvement | Kardco Properties | 2026-04-20 | 2026-05-08 | 18 | $80K |