How long does a Commercial / Multi Family Project permit take in Rutland Park, Calgary?
Median days · Applied → Issued
22 days
Sample: 13 permits, last 24 months
Median days · Issued → Completed
249 days
From permit issuance to completion
City-wide median
42 days
Rutland Park is 20 days faster
Recent examples in Rutland Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10079 | Unspecified | — | 2026-06-04 | 2026-06-26 | 22 | $7K |
| BP2026-04679 | Improvement | Haides Construction | 2026-03-25 | 2026-04-28 | 34 | $30K |
| BP2026-01463 | Improvement | — | 2026-01-31 | 2026-02-27 | 27 | $600K |
| BP2025-21856 | Unspecified | — | 2025-11-11 | 2025-11-13 | 2 | $4K |
| BP2025-17383 | Improvement | Cana Management | 2025-09-05 | 2025-09-11 | 6 | $859K |