How long does a Single Construction Permit permit take in Rosemont, Calgary?
Median days · Applied → Issued
26 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
437 days
From permit issuance to completion
City-wide median
18 days
Rosemont is 8 days slower
Recent examples in Rosemont
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11344 | New | Trickle Creek Custom Homes | 2026-06-19 | 2026-07-31 | 42 | $450K |
| BP2026-00233 | New | Trickle Creek Custom Homes | 2026-01-07 | 2026-02-02 | 26 | $607K |
| BP2025-12155 | New | Alloy Homes | 2025-06-24 | 2025-07-09 | 15 | $657K |
| BP2025-11482 | New | Fox Point Developments | 2025-06-16 | 2025-06-24 | 8 | $546K |
| BP2024-08023 | New | Dream Ridge Homes | 2024-04-29 | 2024-11-01 | 186 | $662K |