How long does a Single Construction Permit permit take in Rosemont, Calgary?

Rolling 24 months · Sample: 5
Median days · Applied → Issued
26 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
437 days
From permit issuance to completion
City-wide median
18 days
Rosemont is 8 days slower

Recent examples in Rosemont

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-11344NewTrickle Creek Custom Homes2026-06-192026-07-3142$450K
BP2026-00233NewTrickle Creek Custom Homes2026-01-072026-02-0226$607K
BP2025-12155NewAlloy Homes2025-06-242025-07-0915$657K
BP2025-11482NewFox Point Developments2025-06-162025-06-248$546K
BP2024-08023NewDream Ridge Homes2024-04-292024-11-01186$662K