How long does a Commercial / Multi Family Project permit take in Rosemont, Calgary?

Rolling 24 months · Sample: 5
Median days · Applied → Issued
50 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
42 days
From permit issuance to completion
City-wide median
42 days
Rosemont is 8 days slower

Recent examples in Rosemont

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2025-14921Improvement2025-07-312026-07-21355$0
BP2025-21114ImprovementLelo Contracting2025-10-292026-01-0669$100K
BP2025-02152Unspecified2025-02-062025-03-2143$5K
BP2025-01549Improvement2025-01-282025-03-1950$200K
BP2024-22584ImprovementRocky Cross Construction North2024-10-232024-11-0513$4K