How long does a Commercial / Multi Family Project permit take in Rosemont, Calgary?
Median days · Applied → Issued
50 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
42 days
From permit issuance to completion
City-wide median
42 days
Rosemont is 8 days slower
Recent examples in Rosemont
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2025-14921 | Improvement | — | 2025-07-31 | 2026-07-21 | 355 | $0 |
| BP2025-21114 | Improvement | Lelo Contracting | 2025-10-29 | 2026-01-06 | 69 | $100K |
| BP2025-02152 | Unspecified | — | 2025-02-06 | 2025-03-21 | 43 | $5K |
| BP2025-01549 | Improvement | — | 2025-01-28 | 2025-03-19 | 50 | $200K |
| BP2024-22584 | Improvement | Rocky Cross Construction North | 2024-10-23 | 2024-11-05 | 13 | $4K |