How long does a Demolition permit take in Rosemont, Calgary?
Median days · Applied → Issued
2 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
61 days
From permit issuance to completion
City-wide median
4 days
Rosemont is 2 days faster
Recent examples in Rosemont
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15604 | Demolition | Project Wize | 2026-08-17 | 2026-08-18 | 1 | $0 |
| BP2026-15191 | Demolition | Gill S Express | 2026-08-11 | 2026-08-12 | 1 | $0 |
| BP2026-13064 | Demolition | Cloverhill Construction | 2026-07-13 | 2026-07-24 | 11 | $0 |
| BP2026-10217 | Demolition | Meech Creek Contracting | 2026-06-05 | 2026-06-19 | 14 | $0 |
| BP2026-05372 | Demolition | Ovis Group | 2026-04-07 | 2026-04-08 | 1 | $0 |