How long does a Residential Improvement Project permit take in Rosemont, Calgary?

Rolling 24 months · Sample: 24
Median days · Applied → Issued
27 days
Sample: 24 permits, last 24 months
Median days · Issued → Completed
224 days
From permit issuance to completion
City-wide median
17 days
Rosemont is 10 days slower

Recent examples in Rosemont

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14777Improvement2026-08-052026-08-2621$45K
BP2026-14941NewBrothers Too Contracting2026-08-072026-08-1912$65K
BP2026-12015ImprovementHome Reinvention2026-06-292026-08-1143$42K
BP2026-13285Improvement2666264 Alberta2026-07-152026-08-1127$81K
BP2026-11345NewTrickle Creek Custom Homes2026-06-192026-07-3142$59K