How long does a Single Construction Permit permit take in Montgomery, Calgary?
Median days · Applied → Issued
31 days
Sample: 34 permits, last 24 months
Median days · Issued → Completed
294 days
From permit issuance to completion
City-wide median
18 days
Montgomery is 13 days slower
Recent examples in Montgomery
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10384 | New | — | 2026-06-08 | 2026-08-17 | 70 | $0 |
| BP2026-11015 | New | 2117663 Alberta | 2026-06-16 | 2026-07-27 | 41 | $329K |
| BP2026-11016 | New | 2117663 Alberta | 2026-06-16 | 2026-07-27 | 41 | $329K |
| BP2026-08714 | New | Maximus General Contracting | 2026-05-19 | 2026-07-22 | 64 | $0 |
| BP2026-01578 | New | The Bass Development Group | 2026-02-02 | 2026-03-20 | 46 | $335K |