How long does a Residential Improvement Project permit take in Montgomery, Calgary?

Rolling 24 months · Sample: 61
Median days · Applied → Issued
29 days
Sample: 61 permits, last 24 months
Median days · Issued → Completed
169 days
From permit issuance to completion
City-wide median
17 days
Montgomery is 12 days slower

Recent examples in Montgomery

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-12028ImprovementCdm Developments2026-06-292026-08-1951$107K
BP2026-12462NewThe Bass Development Group2026-07-062026-08-1742$40K
BP2026-12929ImprovementSuncoast Enclosures2026-07-112026-08-1333$54K
BP2026-11538Improvement2026-06-232026-07-1421$6K
BP2025-14030Improvement2025-07-192026-06-18334$5K