How long does a Residential Improvement Project permit take in Montgomery, Calgary?
Median days · Applied → Issued
29 days
Sample: 61 permits, last 24 months
Median days · Issued → Completed
169 days
From permit issuance to completion
City-wide median
17 days
Montgomery is 12 days slower
Recent examples in Montgomery
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12028 | Improvement | Cdm Developments | 2026-06-29 | 2026-08-19 | 51 | $107K |
| BP2026-12462 | New | The Bass Development Group | 2026-07-06 | 2026-08-17 | 42 | $40K |
| BP2026-12929 | Improvement | Suncoast Enclosures | 2026-07-11 | 2026-08-13 | 33 | $54K |
| BP2026-11538 | Improvement | — | 2026-06-23 | 2026-07-14 | 21 | $6K |
| BP2025-14030 | Improvement | — | 2025-07-19 | 2026-06-18 | 334 | $5K |