How long does a Commercial / Multi Family Project permit take in Montgomery, Calgary?

Rolling 24 months · Sample: 58
Median days · Applied → Issued
93 days
Sample: 58 permits, last 24 months
Median days · Issued → Completed
223 days
From permit issuance to completion
City-wide median
42 days
Montgomery is 51 days slower

Recent examples in Montgomery

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14825Improvement2026-08-062026-09-0833$1K
BP2026-15158Improvement2026-08-112026-08-2615$850
BP2026-07145New2026-04-292026-08-09102$1.5M
BP2025-22813NewGoaldex2025-11-272026-08-05251$778K
BP2024-23969NewQuinterra Homes2024-11-132026-08-04629$719K