How long does a Demolition permit take in Montgomery, Calgary?

Rolling 24 months · Sample: 53
Median days · Applied → Issued
3 days
Sample: 53 permits, last 24 months
Median days · Issued → Completed
38 days
From permit issuance to completion
City-wide median
4 days
Montgomery is 1 days faster

Recent examples in Montgomery

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16126DemolitionPhoenix Treatment Systems2026-08-242026-08-262$0
BP2026-15568DemolitionM2 Excavating and Demolition2026-08-172026-08-192$0
BP2026-15307DemolitionCreative Solutions Contracting Services2026-08-122026-08-153$0
BP2026-14440DemolitionCreative Solutions Contracting Services2026-07-302026-08-1213$0
BP2026-14751DemolitionNewgen Excavating2026-08-052026-08-061$0