How long does a Single Construction Permit permit take in Killarney/Glengarry, Calgary?

Rolling 24 months · Sample: 54
Median days · Applied → Issued
45 days
Sample: 54 permits, last 24 months
Median days · Issued → Completed
315 days
From permit issuance to completion
City-wide median
18 days
Killarney/Glengarry is 27 days slower

Recent examples in Killarney/Glengarry

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-08779NewUrban Indigo Fine Homes Abdullah Holdings2026-05-192026-06-0921$604K
BP2026-04959NewDashmesh Homes2026-03-302026-06-0365$255K
BP2026-04961NewDashmesh Homes2026-03-302026-06-0365$255K
BP2026-06226NewSebo Homes2026-04-172026-06-0145$227K
BP2026-06228NewSebo Homes2026-04-172026-06-0145$227K