How long does a Residential Improvement Project permit take in Killarney/Glengarry, Calgary?
Median days · Applied → Issued
26 days
Sample: 96 permits, last 24 months
Median days · Issued → Completed
168 days
From permit issuance to completion
City-wide median
17 days
Killarney/Glengarry is 9 days slower
Recent examples in Killarney/Glengarry
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16118 | Improvement | — | 2026-08-24 | 2026-08-25 | 1 | $34K |
| BP2026-13547 | Improvement | Candlas Constructors | 2026-07-20 | 2026-08-18 | 29 | $5K |
| BP2026-11072 | Improvement | Sterling Pro Construction | 2026-06-16 | 2026-07-28 | 42 | $0 |
| BP2026-08231 | Improvement | Turn Key Renovations and Contracting | 2026-05-12 | 2026-07-15 | 64 | $284K |
| BP2026-11584 | Improvement | Deck King | 2026-06-23 | 2026-07-14 | 21 | $4K |