How long does a Demolition permit take in Killarney/Glengarry, Calgary?

Rolling 24 months · Sample: 80
Median days · Applied → Issued
4 days
Sample: 80 permits, last 24 months
Median days · Issued → Completed
38 days
From permit issuance to completion
City-wide median
4 days
Same as Killarney/Glengarry

Recent examples in Killarney/Glengarry

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16773DemolitionMaak Homes2026-09-022026-09-086$0
BP2026-16725DemolitionSplendor Group2026-09-012026-09-043$0
BP2026-16738DemolitionMother Earth Contracting2026-09-012026-09-043$0
BP2026-15675DemolitionMeech Creek Contracting2026-08-182026-08-279$0
BP2026-16275DemolitionCreative Solutions Contracting Services2026-08-262026-08-271$0