How long does a Demolition permit take in Killarney/Glengarry, Calgary?
Median days · Applied → Issued
4 days
Sample: 80 permits, last 24 months
Median days · Issued → Completed
38 days
From permit issuance to completion
City-wide median
4 days
Same as Killarney/Glengarry
Recent examples in Killarney/Glengarry
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16773 | Demolition | Maak Homes | 2026-09-02 | 2026-09-08 | 6 | $0 |
| BP2026-16725 | Demolition | Splendor Group | 2026-09-01 | 2026-09-04 | 3 | $0 |
| BP2026-16738 | Demolition | Mother Earth Contracting | 2026-09-01 | 2026-09-04 | 3 | $0 |
| BP2026-15675 | Demolition | Meech Creek Contracting | 2026-08-18 | 2026-08-27 | 9 | $0 |
| BP2026-16275 | Demolition | Creative Solutions Contracting Services | 2026-08-26 | 2026-08-27 | 1 | $0 |