How long does a Commercial / Multi Family Project permit take in Killarney/Glengarry, Calgary?
Median days · Applied → Issued
82 days
Sample: 84 permits, last 24 months
Median days · Issued → Completed
286 days
From permit issuance to completion
City-wide median
42 days
Killarney/Glengarry is 40 days slower
Recent examples in Killarney/Glengarry
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12165 | New | Nexxt Door Homes | 2026-06-30 | 2026-09-10 | 72 | $807K |
| BP2026-11872 | Improvement | Restorers Group The | 2026-06-26 | 2026-08-26 | 61 | $350K |
| BP2026-03331 | New | Samdisha Homes | 2026-03-04 | 2026-08-25 | 174 | $1.1M |
| BP2026-03907 | New | Your Property | 2026-03-13 | 2026-08-11 | 151 | $50K |
| BP2026-02578 | New | Exact Ypc | 2026-02-20 | 2026-08-05 | 166 | $608K |