How long does a Commercial / Multi Family Project permit take in Killarney/Glengarry, Calgary?

Rolling 24 months · Sample: 84
Median days · Applied → Issued
82 days
Sample: 84 permits, last 24 months
Median days · Issued → Completed
286 days
From permit issuance to completion
City-wide median
42 days
Killarney/Glengarry is 40 days slower

Recent examples in Killarney/Glengarry

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-12165NewNexxt Door Homes2026-06-302026-09-1072$807K
BP2026-11872ImprovementRestorers Group The2026-06-262026-08-2661$350K
BP2026-03331NewSamdisha Homes2026-03-042026-08-25174$1.1M
BP2026-03907NewYour Property2026-03-132026-08-11151$50K
BP2026-02578NewExact Ypc2026-02-202026-08-05166$608K