How long does a Single Construction Permit permit take in Glendale, Calgary?

Rolling 24 months · Sample: 16
Median days · Applied → Issued
48 days
Sample: 16 permits, last 24 months
Median days · Issued → Completed
302 days
From permit issuance to completion
City-wide median
18 days
Glendale is 30 days slower

Recent examples in Glendale

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-06333NewFortem Group2026-04-202026-07-2293$256K
BP2026-06335NewFortem Group2026-04-202026-07-2293$256K
BP2026-02010NewBirch Hill Developments2026-02-102026-05-0584$346K
BP2026-01291NewTamson Developments2026-01-282026-02-025$461K
BP2026-00563NewTamson Developments2026-01-142026-01-3016$359K