How long does a Residential Improvement Project permit take in Glendale, Calgary?
Median days · Applied → Issued
23 days
Sample: 64 permits, last 24 months
Median days · Issued → Completed
107 days
From permit issuance to completion
City-wide median
17 days
Glendale is 6 days slower
Recent examples in Glendale
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10262 | Improvement | Renova Homes and Renovations | 2026-06-05 | 2026-09-09 | 96 | $267K |
| BP2026-14394 | Improvement | Bluefish Projects | 2026-07-30 | 2026-08-18 | 19 | $149K |
| BP2026-13453 | Improvement | — | 2026-07-18 | 2026-08-12 | 25 | $1K |
| BP2026-04099 | Improvement | Cleland Contracting | 2026-03-17 | 2026-08-06 | 142 | $25K |
| BP2026-12240 | Improvement | Imanse Construction | 2026-07-01 | 2026-07-29 | 28 | $35K |