How long does a Demolition permit take in Glendale, Calgary?
Median days · Applied → Issued
4 days
Sample: 21 permits, last 24 months
Median days · Issued → Completed
32 days
From permit issuance to completion
City-wide median
4 days
Same as Glendale
Recent examples in Glendale
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14888 | Demolition | Buci S Homes and Development | 2026-08-06 | 2026-08-11 | 5 | $0 |
| BP2026-15007 | Demolition | Bob S Demolition | 2026-08-09 | 2026-08-11 | 2 | $0 |
| BP2026-06876 | Demolition | Raynow Group | 2026-04-27 | 2026-05-05 | 8 | $0 |
| BP2026-05845 | Demolition | Fortem Group | 2026-04-13 | 2026-04-16 | 3 | $0 |
| BP2026-04192 | Demolition | Fortem Group | 2026-03-18 | 2026-03-23 | 5 | $0 |