How long does a Commercial / Multi Family Project permit take in Glendale, Calgary?
Median days · Applied → Issued
105 days
Sample: 31 permits, last 24 months
Median days · Issued → Completed
357 days
From permit issuance to completion
City-wide median
42 days
Glendale is 63 days slower
Recent examples in Glendale
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-09763 | New | Fortem Group | 2026-06-01 | 2026-07-15 | 44 | $554K |
| BP2026-09767 | New | Fortem Group | 2026-06-01 | 2026-07-15 | 44 | $416K |
| BP2026-01927 | New | Troy Custom Homes | 2026-02-09 | 2026-06-21 | 132 | $535K |
| BP2026-02317 | New | — | 2026-02-16 | 2026-06-05 | 109 | $658K |
| BP2026-08532 | Unspecified | — | 2026-05-15 | 2026-05-21 | 6 | $100K |