How long does a Single Construction Permit permit take in Cornerstone, Calgary?
Median days · Applied → Issued
15 days
Sample: 690 permits, last 24 months
Median days · Issued → Completed
171 days
From permit issuance to completion
City-wide median
19 days
Cornerstone is 4 days faster
Recent examples in Cornerstone
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-20184 | New | Jayman Built | 2026-10-21 | 2026-11-13 | 23 | $273K |
| BP2026-19789 | New | Wave Homes | 2026-10-15 | 2026-11-13 | 29 | $540K |
| BP2026-20271 | New | Jayman Built | 2026-10-22 | 2026-11-11 | 20 | $482K |
| BP2026-20296 | New | Shane Homes | 2026-10-22 | 2026-11-10 | 19 | $344K |
| BP2026-20295 | New | Shane Homes | 2026-10-22 | 2026-11-10 | 19 | $341K |