How long does a Commercial / Multi Family Project permit take in Cornerstone, Calgary?
Median days · Applied → Issued
44 days
Sample: 90 permits, last 24 months
Median days · Issued → Completed
165 days
From permit issuance to completion
City-wide median
42 days
Cornerstone is 2 days slower
Recent examples in Cornerstone
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-17222 | Improvement | — | 2026-09-09 | 2026-11-09 | 61 | $30K |
| BP2026-04856 | Improvement | — | 2026-03-27 | 2026-10-29 | 216 | $40K |
| BP2026-18266 | Improvement | — | 2026-09-23 | 2026-10-28 | 35 | $27K |
| BP2026-17669 | Improvement | — | 2026-09-15 | 2026-10-06 | 21 | $10K |
| BP2026-16107 | Improvement | — | 2026-08-24 | 2026-09-30 | 37 | $150K |