How long does a Commercial / Multi Family Project permit take in Cornerstone, Calgary?

Rolling 24 months · Sample: 86
Median days · Applied → Issued
46 days
Sample: 86 permits, last 24 months
Median days · Issued → Completed
171 days
From permit issuance to completion
City-wide median
42 days
Cornerstone is 4 days slower

Recent examples in Cornerstone

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14713Improvement2026-08-052026-09-0834$185K
BP2026-12829Improvement2026-07-092026-09-0255$70K
BP2026-12684Improvement2026-07-082026-09-0256$120K
BP2026-09093Improvement2026-05-232026-07-1755$12K
BP2026-08245Improvement2026-05-122026-06-2948$80K