How long does a Commercial / Multi Family Project permit take in Cornerstone, Calgary?
Median days · Applied → Issued
46 days
Sample: 86 permits, last 24 months
Median days · Issued → Completed
171 days
From permit issuance to completion
City-wide median
42 days
Cornerstone is 4 days slower
Recent examples in Cornerstone
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14713 | Improvement | — | 2026-08-05 | 2026-09-08 | 34 | $185K |
| BP2026-12829 | Improvement | — | 2026-07-09 | 2026-09-02 | 55 | $70K |
| BP2026-12684 | Improvement | — | 2026-07-08 | 2026-09-02 | 56 | $120K |
| BP2026-09093 | Improvement | — | 2026-05-23 | 2026-07-17 | 55 | $12K |
| BP2026-08245 | Improvement | — | 2026-05-12 | 2026-06-29 | 48 | $80K |