How long does a Single Construction Permit permit take in Collingwood, Calgary?

Rolling 24 months · Sample: 10
Median days · Applied → Issued
54 days
Sample: 10 permits, last 24 months
Median days · Issued → Completed
402 days
From permit issuance to completion
City-wide median
18 days
Collingwood is 36 days slower

Recent examples in Collingwood

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14349New2026-07-292026-08-068$0
BP2026-03666NewRedmile Renovations2026-03-102026-04-2041$557K
BP2026-01246NewUrban Indigo Fine Homes Abdullah Holdings2026-01-272026-03-0436$432K
BP2025-03311NewPro Angle Homes2025-02-262025-07-20144$279K
BP2025-03313NewPro Angle Homes2025-02-262025-07-20144$279K