How long does a Residential Improvement Project permit take in Collingwood, Calgary?
Median days · Applied → Issued
26 days
Sample: 44 permits, last 24 months
Median days · Issued → Completed
122 days
From permit issuance to completion
City-wide median
17 days
Collingwood is 9 days slower
Recent examples in Collingwood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-06196 | Improvement | — | 2026-04-17 | 2026-08-26 | 131 | $10K |
| BP2026-14412 | Improvement | Sagecrest Renovations | 2026-07-30 | 2026-08-26 | 27 | $42K |
| BP2026-03448 | Improvement | 9 1 Plumb | 2026-03-06 | 2026-08-20 | 167 | $57K |
| BP2026-11047 | Improvement | — | 2026-06-16 | 2026-08-17 | 62 | $550K |
| BP2026-14014 | Improvement | — | 2026-07-26 | 2026-08-11 | 16 | $3K |