How long does a Demolition permit take in Collingwood, Calgary?
Median days · Applied → Issued
6 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
37 days
From permit issuance to completion
City-wide median
4 days
Collingwood is 2 days slower
Recent examples in Collingwood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15841 | Demolition | Hndl Homes | 2026-08-20 | 2026-08-20 | 0 | $0 |
| BP2026-14174 | Demolition | Cloverhill Construction | 2026-07-28 | 2026-08-04 | 7 | $0 |
| BP2026-01252 | Demolition | Creative Solutions Contracting Services | 2026-01-27 | 2026-06-02 | 126 | $0 |
| BP2026-02580 | Demolition | Redmile Renovations | 2026-02-20 | 2026-03-03 | 11 | $0 |
| BP2026-02117 | Demolition | Partner S Excavation | 2026-02-11 | 2026-02-17 | 6 | $0 |