How long does a Commercial / Multi Family Project permit take in Collingwood, Calgary?
Median days · Applied → Issued
40 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
31 days
From permit issuance to completion
City-wide median
42 days
Collingwood is 2 days faster
Recent examples in Collingwood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08244 | Improvement | Aurora Developments | 2026-05-12 | 2026-06-11 | 30 | $100K |
| BP2025-14159 | Improvement | — | 2025-07-22 | 2026-04-15 | 267 | $0 |
| BP2025-17115 | Unspecified | — | 2025-09-03 | 2025-09-08 | 5 | $12K |
| BP2025-10992 | New | Kamex Construction | 2025-06-09 | 2025-07-29 | 50 | $800K |
| BP2025-12007 | Improvement | — | 2025-06-22 | 2025-07-09 | 17 | $0 |